Fourth Drainage Project, Faisalabad was investigated in terms of operational performance evaluation. The investigations showed a mixed trend of operational performance of various units of FDP (Fourth Drainage Project, Faisalabad) area. The analysis of sump O&M (Operation & Maintenance) data indicated that overall average operational time for FDP sumps was 66%. Ideally the sump system must have remained non-operational only due to DWT (Deep Water Table) rather than any other easons. However, the analysis indicated that DWT was amongst the least occurring reasons for sump closure at FDP area. This aspect highlighted the poor O&M of the system in this area. The S-I-A area of FDP maintained its water table below the design depth (122 cm) with the lowest operational time (49%) mainly due to DWT, indicating that drainage system was over-designed in S-I-A area. The sumps of S-I-B & S-I-C areas did not operate to their potential, indicating the need to improve the sump operation. It was observed that during 2003, only 23% sumps of FDP were in working condition. The high percentage of non-operational sumps (77%) was mainly due to poor O&M of the system. Field data indicate that although the objectives of FDP have been achieved in terms of lowering the water table; however, associated benefits of the project could further be enhanced by improving O&M facilities at the area.