Taunsa barrage located on the Indus River, Pakistan was remodeled/rehabilitated and modernized in year 2005-08, spending more than eleven billion rupees borrowed from the World Bank. Major changes were made in its energy dissipation system/stilling basin and 7 ft high sub-weir/wall was constructed at 800 ft distance downstream of the barrage. The barrage showed poor performance during 2010 floods which caused an uncontrolled breach in its left marginal bund. The sounding and probing data of years 2010-14 showed the development of deep scour pits downstream of the barrage stilling basin and the situation at present is horrifying. The whole stone apron has been washed away, whereas, the concrete block floor along with inverted filters partially or completely disappeared. Moreover, the has river changed its route about 2.5-3.0 km towards Kot Addu, indicating regulation of flow with gates has vanished as the sub-weir is developing uniform flow on the downstream. This study investigates the performance of energy dissipation system in pre and post remodeled scenarios of the barrage and causes for extraordinary drift of the river towards Kot Addu. This research works concludes that remodeling of stilling basin is not rational and is the cause of launching of stone apron and block floor along with inverted filters. Further, construction of sub weir downstream of barrage is responsible for the drift of Indus River towards Kot Addu town.