BIM-Based Time and Cost Tracking of Construction Projects Taking Quality Management into Consideration

Author(s)
Ramy Adel Abdulaziz Civil Engineering Department, Faculty of Engineering – Fayoum University, Fayoum, Egypt.
Ehab Shehata Sobhy Civil Engineering Department, Faculty of Engineering – Fayoum University, Fayoum, Egypt.
Magdy Abdel Aziz El-Yamany Civil Engineering Department, Faculty of Engineering – Fayoum University, Fayoum, Egypt.
Abstract
The construction industry has long suffered from the lack of time and cost tracking systems that take the impact of quality issues into account. Accordingly, emphasizing the integration of Earned Value Management (EVM) and Building Information Modeling (BIM) taking quality management into consideration has become a crucial requirement. The main objectives of this study are to address quality management into BIM and enhance monitoring of project's time and cost performance via addressing the effect of quality issues in order to support making the proper decisions to restore the original plan's progress. Using the capabilities of Application Programming Interface (API) and C# as a powerful programming language, this enhancement is achieved by the development of a BIM-based model including three plugins: Bill of Quantity (BOQ) estimator, Quality inspector, and EVM controller. BOQ estimator tool includes data about element's ID, the corresponding category, geometric properties and the corresponding cost details. Quality inspector tool includes, for project activities as well as elements making up each activity, the related most recent quality status from on-site records. On the other hand, EVM Calculator tool represents the core of the mathematical model that includes planned/budgeted data, actual data and results of EVM analysis providing performance indices and cost/time variances. In this paper, authors focus on providing details about the mathematical model developed to implement EVM Calculator tool via combining the effect of task's quality status on EVM variables. The proposed mathematical approach is validated using four different simulation scenarios. Results of the proposed model were compared with those obtained (and then revised to reflect the effect of quality status on task's/project's time and cost) using primavera P6. The results on comparison show the efficiency of the developed model providing an opportunity to address the effect of quality issues into EVM analysis that would reduce calculation time and eliminate chances of human errors associated with altering of results.
Publication Details
Page(s) 1737-1753
Published Journal: International Journal of Membrane Science and Technology, Volume: 10, Issue: 1, Year: 2023

Request the full text from PASTIC

Keywords
Quality management, Building Information Modeling, Time-Cost Tracking, Earned Value Management
References
Maria J. R.,Jan M.,Gernot S.,Erik S.,Rob P.,Jonas B.,David R,Timmy A. R .2020 .The next normal in construction How disruption is reshaping the world's largest ecosystem. McKinsey & Company June, : .
Boton Gilles. .2015 .. The Challenge of Level of Development in 4D/BIM Simulation Across AEC Project Lifecyle. A Case Study. Procedia Engineering, 123 : 59-67.
Sloot R.N.F.,Heutink A.,Voordijk J.T. .2019 .Assessing usefulness of 4D BIM tools in risk mitigation strategies. , 106 : 102881.
Crowther James,Saheed O. Ajayi James .2021 .Impacts of 4D BIM on construction project performance. International Journal of Construction Management, 21(7) : 724-737.
Jin Vineeth. .2019 .Using 4D BIM to assess construction risks during the design phase. Engineering Construction & Architectural Management, 26 : 2637-2654.
Faris E.,Sepehr A. .2020 .Developing a framework to revolutionise the 4D BIM process: IPD-based solution. Construction Innovation, 20(3) : 401-420.
Peter S. .2016 .Project cost management with 5D BIM. , 226 : 193-200.
Amjed N.,Sawsan M. .2019 .The Benefits of and Challenges to Implement 5D BIM in Construction Industry. Civil Engineering Journal, 5(2) : .
Kehily D,Underwood J .2017 .Embedding life cycle costing in 5D BIM. , 22 : 145-167.
Tochukwu M.,David H.,David O H. .2020 .Implementing 5D BIM on construction projects: contractor perspectives from the UK construction sector. , 18(6) : 1867-1888.
C. Bob T.,Thomas K .1999 .MEP Coordination in Building and Industrial Projects, center for integrated facility engineering 54.. , : .
Ahmad J.,Julien L. .2015 .An Integrated BIM System to Track the Time and Cost of Construction Projects: A Case Study. Journal of Construction Engineering, 579486 : .
Tetsuya M. .1997 .Construction manageability planning - A system for manageability analysis in construction planning. International Symposium on Automation and Robotics in Construction, 6(3) : 175-191.
Faris E.,Sepehr A.,M. Reza H.,Soliman A.,Mark G. .2019 .Integrated project delivery with BIM: An automated EVM-based approach. , 106 : 102907.
Russell K.,Toby H. .2015 .Construction Project Control Methodologies And Productivity Improvement: EVM, BIM, LBM. , 10 : .
C. Cárdenas P.,Zapata N.,Lozano N. .2018 .Building Information Modeling 5D and Earned Value Management methodologies integration through a computational tool. , 33(3) : 263-278.
Park S.,Inhan K. .2015 ."BIM-Based Quality Control for Safety Issues in the Design and Construction Phases." Archnet-IJAR:. International Journal of Architectural Research, 9(3) : 111-129.
Choi J.,Lee S.,Kim I. .2020 .Development of Quality Control Requirements for Improving the Quality of Architectural Design Based on BIM. Applied Sciences, 10(20) : 7074.
Amin A.,Mehrdad A.,Heng L.,Tuan N.,Alireza B.,Ali R. .2020 .Sensor-based safety management. Automation in Construction, 113 : 103128.
Reinbold A.,Seppänen O.,Peltokorpi A.,Singh V.,Dror E. .2019 .(Annual Conference of the International Group for Lean Construction). International Group for Lean Construction (IGLC)., : 1141-1150.
Hong Y.,Chen W.,Z. W. .2018 .Developing a Quality-Embedded EVM Tool to Facilitate the Iron Triangle in Architectural, Construction, and Engineering Practices. Journal of Construction Engineering and Management, 144 : .
Project Management . .Institute (PMI). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (4th ed. PMI Publications., : .
0

Citations

0

Downloads

101

Views