An Interim evaluation of environmental aspects of the Mangla watershed management project.
Author(s)
Syed Wali Waheed WAPDA Environmental Cell, Lahore, Pakistan
Syeda Bushra Waheed Hydro-Electric Planning Organization, WAPDA, Lahore, Pakistan
Charles Adamson Neelum-Jhelum Hydropower Project WAPDA
Abstract
Mangla is the second largest dam in Pakistan, commissioned in 1967. A Watershed Management Project for the dam’s catchment area was initiated simultaneously with the main objective of reducing sediment inflow into the Mangla reservoir and hence to prolong its life. An evaluation of the watershed management program was carried out. This paper describes the environmental aspects of the project observed during the evaluation, and suggests measures for improving the reforestation formula, and for setting up a monitoring network that could yield data for realistic assessment of the watershed’s performance.
Publication Details
Page(s) 14-28
DOI DOI not available
Published Journal: Pakistan Journal of Environmental Science, Volume: 1, Issue: 2, Year: 2002
Keywords
Keywords are not available for this article.
References
References are not available for this document.
Citations
Citations are not available for this document.
0

Citations

0

Downloads

83

Views

Copyright ©  PASTIC National Center, Islamabad www.pastic.gov.pk